EiS Projects Initialize Process


This report/process populates Projects Measures on projects and Task levels in EiS Project datamart from Project inception date till datamart start Date. These balances are used for calculating QTD, YTD and ITD values for further processing of project datamart and for reporting purpose in the Projects module. EiS Projects Initialize Process will summarize all the projects data into one row for each project/task based on the Start Date for the datamart that is defined in the Setting tab. Execute this process only once on Project Datamart initialization, only Oracle E-Business Suite Developer/System Administrator can execute this process.


Prerequisite Setup: 

  1. Navigate to Setup > Projects > Settings.
  2. Select the Connection pointing to EBS Database.
  3. Enter the Start Date for Datamart and click Save.


To run the EiS Projects Initialize Process:

  1. Navigate to Reports > All Reports.
  2. Search for EiS Projects Initialize Process in all reports tab.
  3. Click on Run icon to navigate to Submit page.
  4. Click on Submit button to run the process.

EiS Projects Initialize Process Parameters


Responsibility: Select a valid EBS responsibility from the Responsibility drop down.


Debug: This parameter is required to debug the execution of initialization process. If this is passed as Yes, it will log additional information which is more relevant to System Administrator and Developers to debug the issues. User can run the report with default value as No.